Road rehabilitation project in the historical center from the city of Salzwedel Mixed-in-plant - method with EvoCrete® ST

  • Location: Salzwedel
  • Area: 20.000 m²
  • Excution time: 2002 / 2003
  • Construction period: 4 weeks
  • Binding agent: 150 kg / m³
  • Milling depth: 25 cm

Salzwedel: Road rehabilitation work, mixed-in-plant method